Securities Under Scrutiny
By Rachit Saini
|
When Can Courts Restrain a Call on Bonds? Both performance bonds and payment-security bonds are central features for risk allocation between builders and property owners. Australian courts have consistently emphasised that unconditional performance bonds operate on a “pay now, argue later” basis, which preserves the beneficiary’s right to payment on unresolved claims or disputes. However, the recent Supreme Court decision in Alstef Australia Pty Ltd v Brisbane Airport Corporation [2026] NSWSC 764 highlights an evolution in judicial willingness to scrutinise the operation of payment-security bonds. |
The Facts:
Brisbane Airport Corporation (BAC) engaged Alstef to design and construct a baggage handling system for Brisbane Airport’s domestic terminal. The DTB contract comprised of five bank guarantees:
- Two performance bonds, which are an unconditional undertaking given by Australia and New Zealand Banking Group Limited (ANZ) for failing to fulfil a contractual obligation.
- Three payment-security bonds, procured by Alstef to secure progress payments from BAC for unfixed goods and materials.
Following the detection of a structural steel defect, both parties entered termination notices for the DTB contract, yet the dispute remained on who validly did so first. Alstef’s sought an interim injunction to restrain BAC from calling on any of the five bank guarantees, pending the resolution of the termination dispute.
The Judgement:
The Court refused to provide an interim injunction over the performance bonds but did grant an injunction over the payment-security bonds. The outcome with performance bonds parallels that of Electricity Generation Corp v Woodside Energy & Simic v NSW Land and Housing Corp, but the outcome with payment-security bonds is novel.
-
Why was interim injunction for performance bonds refused?
Williams J held it was of high weight that the bonds acted in a “pay now argue later” regime, allowing BAC to obtain payments regardless of any disputes raised by Alstef to avoid the risk of BAC being “out of pocket pending a final determination”.
The Court was also unconvinced that a call on the bonds could cause Alstef significant financial harm and placed a low weight on the reputational damage that may come with it. Hence, the issue of depriving BAC of the contractual benefit of exercising the bond rights outweighed the issue for Alstef in the financial and reputational damage.
- Why was interim injunction for payment-security bonds granted?
The payment-security bonds simply apply to payment and title for unfixed goods and materials. Alstef held a strong prima facie case that clause 12.7(a)(ii) held no effect under s 200 of the Building Industry Fairness (Security of Payments) Act 2017 (Qld) (‘BIF Act’) since the contract provisions “exclude, limit or change” the operation of the Act. The Court thus found it of high weight that clause 12.7(a)(ii) had the effect of undermining the entitlement to progress payments since the payment for unfixed goods and materials were immediately re-secured dollar-for-dollar by a bank guarantee.
Similarly on a prima facie basis, the Court was satisfied that with the title to the goods being passed to BAC, retaining the bonds would amount to unconscionable conduct, as per s 21 of the Australian Consumer Law 2010 (Cth) (‘ACL’).
What this decision means for the Building and Construction Industry?
The Supreme Court decision indicates the following three takeaways about security law.
- It is strongly arguable that performance bonds act as “risk allocation devices” under a DTB Contract, allowing the defendant to have recourse to them without proving its claims.
- A relevant clause of a contract may be rendered void under s 200 of the BIF Act, as it effectively excludes the plaintiff’s statutory right to progress payments for unfixed goods.
- Retaining the payment security bonds would be unconscionable under s 21 of the ACL as the goods and materials had already been paid for and title has been passed to the defendant.
If you have concerns about your contractual security rights or obligations in light of this decision, Crisp Law stands ready to advise and support you.
Contact Crisp Law for advice and information:
Telephone: +61 2 8042 8701
Email: admin@crisplaw.com.au
References
- Alstef Australia Pty Ltd v Brisbane Airport Corporation [2026] NSWSC 764
- Electricity Generation Corporation (t/as Verve Energy) v Woodside Energy Ltd [2014] HCA 7
- Simic v New South Wales Land and Housing Corporation [2016] HCA 47
- Building Industry Fairness (Security of Payment) Act 2017 (Qld) s 200
- Australian Consumer Law (Schedule 2 to the Competition and Consumer Act 2010 (Cth)) s 21